QUESTION 141
A company is executing a critical project with many particular interests and impacts on quality. Which project artifact can be used to document who can influence the use of one kind of resource over another?
A. Risk register
B. Resource management plan
C. Project schedule
D. Stakeholder register
Correct Answer: B
QUESTION 142
An agile team adds a user story related to architecture improvement in the current iteration. The product owner is not pleased but the team says it must be added to the current iteration to minimize risk. What should the product owner do?
A. Allow the team to add the improvement to the current iteration after considering the risk.
B. Review project integration management to determine which iteration should have the improvement added.
C. Request the team to add it to the next iteration as the risk must be properly assessed.
D. Analyze the project schedule to determine which iteration should have the improvement added.
Correct Answer: A
QUESTION 143
The project manager needs to communicate a large amount of information to a large group of people. The project manager achieves this by using an intranet, knowledge repository, and e-learning tools. What kind of communication is being used?
A. Interactive
B. Push
C. Pull
D. Interpersonal
Correct Answer: C
QUESTION 144
A program consists of four agile teams Each team has a separate daily standup Later each day, there is another standup meeting attended by one member from each team. Which Scrum technique is this?
A. Large Scale Scrum (LeSS)
B. Disciplined Agile (DA)
C. Scaled Agile Framework (SAFe)
D. Scrum of Scrums
Correct Answer: D
QUESTION 145
What is the next step for a business analyst after the stakeholders have validated the requirements?
A. Update the project management plan.
B. Update the requirements traceability matrix.
C. Update the work breakdown structure (WBS).
D. Update the requirements.
Correct Answer: B
QUESTION 146
Which two techniques should be used to improve a process or product? (Choose two)
A. Lesson learned
B. Lunch and learn
C. Feature enhancement
D. Scope enhancement
E. Retrospective
Correct Answer: CE
QUESTION 147
ln which project performance domain is the work breakdown structure (WBS) developed?
A. Development approach and life cycle
B. Planning
C. Project work
D. Delivery performance
Correct Answer: B
QUESTION 148
While gathering nonfunctional requirements for developing a portal, which three aspects should a business analyst check to ensure that the solution developed will be fit for use by the customer? (Choose three)
A. Uptime
B. Ease of use
C. Reliability
D. Data integrity
E. Navigation
Correct Answer: ACD
QUESTION 149
A project has encountered some difficulties that will impact the project management plan and the project management process. Which two actions should the project manager take? (Choose two)
A. Perform integrated change control.
B. Submit a change request
C. Perform integrated project management
D. Perform a risk analysis.
E. Perform quality management
Correct Answer: AD
QUESTION 150
A Scrumban team member wants to know what work has been completed this week Which chart should the team member review?
A. Kanban chart
B. Gantt chart
C. Feature chart
D. Burndown chart
Correct Answer: D
QUESTION 151
An obstacle has been identified and could potentially hinder the project’s progress. Where should this obstacle be documented?
A. Stakeholder register
B. Risk register
C. Assumption log
D. Communications management plan
Correct Answer: B
QUESTION 152
A business manager has an idea for a new product they feel will be highly profitable to the business. How can the product idea be validated in the market before developing the product?
A. Launch a prototype to get customer feedback.
B. Present the idea to a focus group for feedback.
C. Review similar products in the market for gap analysis.
D. Perform a SWOT analysis to compare it with competing products.
Correct Answer: A
QUESTION 153
A new vendor offers a one-time price break but cannot guarantee they will still be in the local market for any future projects. Which project management approach should be used to take advantage of this offer?
A. Agile
B. Hybrid
C. Iterative
D. Predictive
Correct Answer: B
QUESTION 154
In an agile project, when should story prioritization be performed?
A. Within the first half of the project
B. Within the first half of the project, except for high-priority stories
C. Anytime during the project
D. Anytime during the project if the project manager allows it
Correct Answer: C
QUESTION 155
Which life cycle does the level of formality for a solution documentation depend on?
A. Portfolio life cycle
B. Program life cycle
C. Product life cycle
D. Project life cycle
Correct Answer: D
QUESTION 156
What is the projected annual yield of a project investment, incorporating both initial and ongoing costs into the estimated percentage growth rate that the project will have?
A. Internal rate of return
B. Annual rate of return
C. Net present value
D. Return on investment
Correct Answer: A
QUESTION 157
A practitioner interviewed a sample of users and has captured their experiences using the system. What business tool should the practitioner use to capture the solution value and benefits?
A. Event list
B. Product box
C. Use case
D. User story
Correct Answer: D
QUESTION 158
A project team is reviewing the sprint, and the scrum master is concerned about the team creating features that are not needed. Which is a key factor for delivering the a highest value to the customer?
A. Product ownership
B. Scope refinement
C. Stable environment
D. Team coach
Correct Answer: A
QUESTION 159
A product owner and team members are working on tasks to be completed in the next project iteration. What should they do at this point in the project?
A. Perform an iteration retrospective with the team.
B. Follow the plan as initially designed by the team and stakeholders.
C. Shorten the delivery time of the next iteration in order to increase the management reserve.
D. Refine the task list, incorporating tasks not completed in previous iterations.
Correct Answer: D
QUESTION 160
Which of the following artifacts is the business analyst’s main responsibility?
A. Business case
B. Project charter
C. Product scope
D. Project scope
Correct Answer: A
We use cookies to improve your experience, including essential cookies required for the website to function. By continuing, you agree to our use of cookies. Learn more.
We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.
Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.
Advertisement cookies are used to provide visitors with customised advertisements based on the pages you visited previously and to analyse the effectiveness of the ad campaigns.
Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.