Question 179 (Q182)


You are the project manager of the GHQ Project. You are working with your project team to create the project network diagram. You have created the PND and are identifying the critical path with your team using your project management information system. All of the activities on the critical path are showing in red in the software that you are using to evaluate the critical path.
What are schedule activities on the critical path called?

Checking access…

Discussion

Loading comments…

← Back to question bank