Question 178 (Q181)
Maurice is the project manager of the NHQ Project and his project team has just finished the project activities. The quality control team reports that the project deliverables are perfect. The only thing left to in the project is to verify scope. This process will be performed by the project stakeholders. Maurice is required to submit a final project report and report on the project performance. Maurice’s project had a budget of $234,000 but the project spent $245,000. In the final report management wants to know the project’s cost performance index (CPI). What value should Maurice report?