PMI Scheduling Professional (PMI-SP)® — Question 180
PMI SP Part 10 · question 180 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 180 (Q183)
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they’d like to know what your schedule variance is. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is the schedule variance for this project?