Question 97 (Q99)


A project team is preparing to start a high-visibility construction project with strict regulatory requirements and significant environmental risks. The sponsor emphasizes the need to avoid delays and cost overruns. The risk manager’s initial evaluations highlight potential challenges related to approvals, weather conditions, and resource availability. What should the risk manager do?