Question 96 (Q98)


A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says if that if there is less than a 60% chance of rain, construction should continue. What should the risk manager do next to find out the correct limit?