Question 98 (Q100)


The implementation phase of a construction project is underway. A high-priority risk involving material shortages threatens the timeline. The risk response plan includes sourcing alternative suppliers and adjusting the work schedule. Some team members suggest prioritizing tasks that do not rely on the delayed materials to avoid disruption. What should the risk manager do?