Question 32
A large infrastructure project is currently in the planning phase, and the risk manager is developing a comprehensive risk register. During a risk identification workshop, stakeholders identified several potential risks, including supply chain disruptions, regulatory changes, and technical failures. Which step is critical to ensure that the risk register accurately reflects the potential impact and likelihood of identified risks?