Question 33


The project team has completed risk identification, scoring. and prioritization. The results are as follows:
Low priority: 32 risks and 8 opportunities Medium priority: 28 risks and 5 opportunities High priority: 17 risks and 2 opportunities
The risk manager needs to determine which items should undergo quantitative analysis to refine impact estimates and develop response plans. Which risks and opportunities should be selected for quantitative analysis and response planning?