PMI Risk Management Professional (PMI-RMP)® — Question 31
PMI RMP Part 2 · question 31 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 31
A construction company is kicking off a new project to build a residential high-rise building. The project manager has been facilitating scoping sessions, in which multiple risks have been identified. The project manager has provided the risk manager with the meeting minutes that detail these risks. What should the risk manager do first to ensure the risks identified in the meeting minutes are incorporated into the project management plan?