Question 30


During the execution phase of a project, a team of selected experts is tasked with evaluating the projects risk management processes. The team begins by thoroughly examining the risk register to assess the number of risks that have materialized, along with the effectiveness of the corresponding response plans. The team also investigates the occurrence and potential impact of any unidentified risks that were not documented earlier. The team analyzes how the risk management processes align with the project s objectives and provides recommendations for improvement.
Which type of activity are the team of risk experts performing?