An interim risk manager has been assigned to a project team because the primary risk manager is out on unexpected leave. The project manager shares all of the risk management artifacts with the interim risk manager. During a meeting, several stakeholders disagree on which risks should be mitigated due to the amount of resources required to implement the mitigations.
How should the risk manager respond to ensure that resources are allocated effectively to risk mitigations?