PMI Risk Management Professional (PMI-RMP)® — Question 28
PMI RMP Part 2 · question 28 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 28
During a project’s planning phase, the project team along with the project manager, identified four significant risks that could potentially impact the project. The team also evaluated the contingency reserve established to address these risks. However, during the execution phase, Risk R2 materialized, affecting the project. What is the remaining amount of the contingency reserve in this scenario?

Checking access…

Discussion
Loading comments…