PMI Construction Professional (PMI-CP) — Question 35
PMI CP Part 2 · question 35 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 35
A construction professional is assigned to a project to build a power plant. The project is in the closing phase. During the lessons learned meeting, everyone agrees that handling the many interface points on the project efficiently was challenging, causing cost overruns and schedule delays. During the next executive meeting a few months later, the construction professional proposes investing in an interface management system (IMS).
Which three benefits should the construction professional highlight to convince the executive team to adopt this software? (Choose 3)