PMI Construction Professional (PMI-CP) — Question 34
PMI CP Part 2 · question 34 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 34
A construction professional meets with their interface manager to streamline the project’s interface management processes. The assessment shows that the project’s (IM) maturity stage is 4. The complexity and project risk levels are high. The construction professional and the interface manager determine that a fully automated system that shares key common data should be implemented. They further discuss how interface points (IPs) and interface agreements (IAs) will be managed throughout the project life recycle.
Which document will the construction professional use to record all the information?