PMI Construction Professional (PMI-CP) — Question 36
PMI CP Part 2 · question 36 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 36
A key donor, with no project management background, reviews the progress report for one of the high-profile projects to build a power plant. During the review, the donor noticed that the cost performance index (CPI) was 0.5, but they do not know how to interpret this data. The donor decides to consult a construction professional about this. What should the construction professional advise the key donor?