Question 29


A construction professional is implementing a housing project. The construction professional used instant messaging to communicate with the contractor and exchange drawings. One day during a site visit, the construction professional discovers that all of the drywall work on the first floor has been constructed based on the design drawings for the second floor. Extensive rework is required to correctly implement the design, and there will be a 1-week delay.
What should the construction professional have done to prevent this from happening?

Checking access…

Discussion

Loading comments…

← Back to question bank