PMI Construction Professional (PMI-CP) — Question 30
PMI CP Part 2 · question 30 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 30
A project management office (PMO) is auditing a construction project and its delivery when they discover that the project does not have a risk register. The project manager believes that the daily standups are a better way to manage risks. The PMO approaches a construction professional to help with this situation. How should the construction professional respond to the project manager to help them understand the need for the risk register?