PMI Construction Professional (PMI-CP) — Question 28
PMI CP Part 2 · question 28 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 28
A construction professional is working on a large complex project to build a first of its kind technology. The project is progressing toward detailed design and is required to go through a phase gate that must include a detailed risk register. The construction professional has identified a number of risks that may require contingency. What should the construction professional do?