Question 27


A project is in the pre-award phase, and the procurement team is reviewing the clauses to be incorporated into all contracts. Based on lessons learned in recent projects, it has been decided that adjustments will be made to the standard clauses. The aim of the updates is to reduce the effects of changes in scope, manage the changes in budget and schedule, and create a mechanism to handle claims that cannot be closed and require another method for closure.
Which clauses should the construction professional review and configure?