PMI Construction Professional (PMI-CP) — Question 26
PMI CP Part 2 · question 26 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 26
A construction professional is assigned to a new project to build a gas-to-liquids (GTL) plant in an medium-risk industrial area. The project is high profile with a large number of stakeholders involved. Due to the nature of the project, the construction professional decides to leverage a technology that will help with scope and change management. Upon evaluation, a suitable solution was selected, and a proposal was submitted to the sponsor as this was not part of the original approved project budget. The sponsor rejects the proposal stating that they do not see the benefit of leveraging any sort of technology on the project.
How should the construction professional respond to the sponsor?