Question 108


During the planning phase of a construction project, it is discovered that there are insufficient areas available for the storage of excavated materials. A stakeholder offers some room on their premises, which would be beneficial to the project. The construction professional requests and receives approval from the designer to proceed. However, there is now a slight cost increase, which needs to be approved by the cost control department. After 2 weeks, the cost control department has not responded. During this window, the stakeholder calls to let the construction professional know that the area has been given to someone else.
What should the construction professional have done to prevent this from happening?