Question 107
A development firm is planning to issue a request for proposal (RFP) for the construction of a major hospital. The firm is evaluating different types of contracts and delivery methods, which will be disclosed in the RFP. The firm believes in teamwork, collaboration, and shared risks and rewards. They are also focused on choosing a delivery method that will reduce conflicts, claims, and the risk of document misinterpretation.
Which delivery method should the construction professional advise the firm to use?