PMI Construction Professional (PMI-CP) — Question 109
PMI CP Part 6 · question 109 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 109
A construction professional is leading a project to build a new corporate campus and is working with an excavation subcontractor in preparation for construction. The construction professional is finalizing the details for the overall footprint, but it is possible the area for excavation may change. Which contract type should the construction professional select for this work?
Checking access…