QUESTION 1
Which function belongs to the capacity management function of Huawei NetEco?
A. Automatically evaluates the space, power, and cooling (SPC), and optimizes the server installation position.
B. Generates an inspection report by one click and automatically assesses the inspection health status.
C. Automatically detects asset status and generates asset reports.
D. Detects the air conditioner refrigerant capacity and generates an alarm when the capacity is insufficient.
Correct Answer: A
QUESTION 2
Which of the following statements are true about the integrated PDF in the FusionModule2000?
A. For a 1100 mm deep PDF, cables can only be routed from the top
B. The integrated PDF cannot supply power to air conditioners.
C. A level B SPD is used for the integrated PDF in standard configuration.
D. The integrated PDF can be installed on an ESD floor or a concrete floor.
Correct Answer: AD
QUESTION 3
In the FusionModule2000, the skylight actuator can control the rotating skylight in the aisle containment of the modular data center.
A. TRUE
B. FALSE
Correct Answer: A
QUESTION 4
Which of the following components can convert PoE signals into WiFi signals?
A. VCN
B. Skylight actuator
C. AC actuator
D. WiFi module
Correct Answer: D
QUESTION 5
Which of the following statements about the functions of the AC PDB is false?
A. Supplies power to the extinguishant control panel.
B. Supplies power to air conditioners.
C. Supplies power to sockets in the module.
D. Supplies power to fans.
Correct Answer: C
QUESTION 6
Which of the following are the main positioning scenarios of the Fusion Module 500é”›?
A. Large-sized enterprise data center
B. Bank outlets
C. Network access of small- and medium-sized enterprises
D. Government township outlets
Correct Answer: BCD
QUESTION 7
The FusionModule800 has two power distribution architectures: N system and N+1 system.
A. TRUE
B. FALSE
Correct Answer: A
QUESTION 8
When will the bypass module of Huawei integrated UPs start to work?
A. Both the active and standby ECMs are abnormal.
B. The UPS works in ECO mode, and the bypass voltage is within the preset range.
C. The power module overload times out.
D. The UPS is just powered on and the inverter is not started.
Correct Answer: BCD
QUESTION 9
Which of the following devices must be installed in the network cabinet of the Fusion Module2000 in standard configuration?
A. VRLA battery, power and environment monitoring switch
B. SmartLi battery module, rPDU
C. In-cabinet air conditioner, PDU5000
D. NetEco server, ECC800-Pro
Correct Answer: D
QUESTION 10
There are three types of adjustable bases for installing FusionModule2000 cabinets: 250 mm wide, 600 mm wide, and 800 mm wide.
A. TRUE
B. FALSE
Correct Answer: B
QUESTION 11
Which of the following statements are true about the conditions for the integrated UPs to transfer to equalized charging automatically?
A. The SOC is less than the setting.
B. The battery temperature exceeds 45掳C during charging.
C. In charge state, the battery current is greater than the transfer-to-equalized charging current.
D. The number of consecutive float charging days reaches the setting.
Correct Answer: ACD
QUESTION 12
Which of the following statements about the risks of lead-acid battery storage is false?
A. If lead-acid batteries are stored properly, they will pass the discharge test even if they have been stored for a long time.
B. If lead-acid batteries are stored for a long time, their internal resistance will increase.
C. If lead-acid batteries are stored for a long time, their self-discharge will cause the battery capacity to attenuate.
D. If batteries are stored in a high-temperature environment for a long time, the possibility of battery bulging increases.
Correct Answer: A
QUESTION 13
On the SmartLi WebUI, operator-level users can export system fault data but have no permission to clear faults.
A. TRUE
B. FALSE
Correct Answer: B
QUESTION 14
Which of the following statements is false about the startup and shutdown of the SmartLi battery cabinet?
A. To shut down the SmartLi, press and hold the POWER ON/OFF button on each battery management module for more than 1 seconds.
B. If multiple battery cabinets are combined, press and hold the POWER ON/OFF button on the battery management module of each cabinet for more than 2 seconds.
C. Before starting the SmartLi, ensure that the ready switch on the battery management module is turned on.
D. If batteries are powered off and will not be charged for more than a month, remove the battery management module.
Correct Answer: A
QUESTION 15
Which input and output system does the UPS2000-G-6K support?
A. Single-phase input, single-phase output, mains and bypass single source.
B. Single-phase input, single-phase output, mains and bypass dual sources.
C. Three-phase input, single-phase output, mains and bypass dual sources.
D. Three-phase input, three-phase output, mains and bypass single source.
Correct Answer: A
QUESTION 16
Which statement about the UPS2000-G-6KRTS is false?
A. The UPS is a standard model with short backup time.
B. The UPS can be tower-mounted or rack-mounted.
C. The UPS connects to external batteries.
D. The rated input capacity of the UPS is 6 kVA.
Correct Answer: D
QUESTION 17
Which of the following statements is true about the wiring diagram of the UPS2000-G-20K?

A. The wiring mode is single-phase input, single-phase output, mains and bypass single source.
B. The wiring mode is three-phase input, three-phase output, mains and bypass dual sources.
C. The wiring mode is three-phase input, three-phase output, mains and bypass single source.
D. The wiring mode is three-phase input, single-phase output, mains and bypass single source.
Correct Answer: D
QUESTION 18
The optional communication cards for the UPS2000-G are only the Modbus card and SNMP card.
A. TRUE
B. FALSE
Correct Answer: B
QUESTION 19
Which of the following statements is false about the features of the modular UPS5000-E?
A. On-demand capacity expansion is supported, ensuring smooth capacity expansion.
B. The UPs can be maintained from the front.
C. All components use redundant and modular design, which eliminates single points of failure.
D. SNMP, modbus, and dry contact cards are provided in standard configuration.
Correct Answer: C
QUESTION 20
The UPS5000 antiseismic kit is applicable to earthquake-prone zones. The kit provides support for cabinets and prevents them from tilting when an earthquake with an intensity of 9 or below occurs.
A. TRUE
B. FALSE
Correct Answer: A
We use cookies to improve your experience, including essential cookies required for the website to function. By continuing, you agree to our use of cookies. Learn more.
We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.
Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.
Advertisement cookies are used to provide visitors with customised advertisements based on the pages you visited previously and to analyse the effectiveness of the ad campaigns.
Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.