Program Management Professional (PgMP)® — Question 96
PMI PGMP Part 5 · question 96 of 200 in the Program Management Professional (PgMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 96
After taking over a program, a program manager reviews the program’s status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000.
Based on this information, the program manager determines which of the following?
Checking access…

Discussion
Loading comments…