Program Management Professional (PgMP)® — Question 95
PMI PGMP Part 5 · question 95 of 200 in the Program Management Professional (PgMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 95
You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder’s conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?