PMI Risk Management Professional (PMI-RMP)® — Question 51
PMI RMP Part 3 · question 51 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 51 (Q52)
A project team is working on a high-stakes project with a risk appetite that tolerates up to a 10% cost overrun. During the planning phase, four potential risks are identified. The total project budget is US$1,000,000. Which risk should the risk manager prioritize first, based on the risk appetite?