PMI Risk Management Professional (PMI-RMP)® — Question 50
PMI RMP Part 3 · question 50 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 50 (Q51)
During a risk planning session, the project team identifies a significant risk of resource deficits along with a potential opportunity to secure additional funding. Some team members suggest focusing on risks with immediate impact, while others propose addressing all identified risks and opportunities equally. What should the risk manager do?