Question 160 (Q163)
A large-scale IT system implementation project has multiple phases, including design, development, testing, and deployment. As the project progresses into the testing phase, stakeholders voice concerns about potential delays to the risk manager. Although the project team has been submitting weekly progress reports, the stakeholders feel these reports lack actionable insights.
What should the risk manager do?