PMI Risk Management Professional (PMI-RMP)® — Question 159
PMI RMP Part 9 · question 159 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 159 (Q162)
It typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours. 3 hours. Using the project evaluation and review technique (PERT) to estimate duration, how many hours should the project manager plan to schedule the task, taking into account all the positive and negative risk factors?