Question 144 (Q146)
A risk manager is developing the risk management plan and schedules risk planning workshop at the start of the project. Upon receiving the invitation, a senior stakeholder emails the project manager stating that a risk management a plan is not needed since this is a small project, and the absence of a plan will reduce costs. What should the risk manager do?