Question 143 (Q145)


During the project’s kickoff meeting, the customer shares potential events that could arise during the project execution phase and suggests they be adequately planned for. The project manager requests the risk manager documents the events and ensures this exercise IS repeated during upcoming project meetings. What should the risk manager do?