Question 99


A construction professional is assigned to a critical building project for a high-profile client with many stakeholders and communications channels. The client requests that the construction management firm start construction as soon as possible. During the planning phase, the project team is about to start using the Compass tool when the project sponsor suggests doing this later to expedite planning and commence with the construction as soon as possible.
What should the construction professional do?