A construction professional is managing a mall refurbishment project. At the weekly progress meeting with the main contractor, the construction professional asks when the long-lead items’ delivery plan will be finalized. The construction professional has been receiving vague updates and time is running out. What should the construction professional do to address the communication gap and avoid impacts to project delivery?