PMI Construction Professional (PMI-CP) — Question 86
PMI CP Part 5 · question 86 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 86
A construction professional is assigned to a new build project and is currently preparing with the team to commence with the risk management activities. The team conducted interviews, reviewed project documents and lessons learned, and identified as many risks as possible. The team added the risks to the project’s risk register. What should the construction professional do once the risks have been identified?