Question 85


A construction professional is developing the risk strategy for a project that will deliver a new building for a primary school. After careful analysis of the stakeholders’ requirements and government regulations, the construction professional recommends the use of a new design that differs from the existing buildings on the campus. What positive risk should the construction professional use to support this recommendation?