PMI Construction Professional (PMI-CP) — Question 7
PMI CP Part 1 · question 7 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 7
At a weekly progress meeting for the construction of a new hospital using a lump-sum contract and design-build (DB) delivery method , an IT manager points out that the telephone and data room that has already been constructed is too small to hold all of the IT equipment. The only solution is to demolish a nearby bathroom to enlarge the IT room, which will cause a cost increase and schedule delay for the project.
What should the construction professional have done to avoid this situation?