In a construction project already underway, a couple of changes occur that require immediate implementation to avoid slowing down other subcontractors. Due to the cost significance of the changes, the construction professional requested that the subcontractor affected by those changes submit urgent change requests to the procurement department. One week after submitting their change requests, the subcontractor complains that they did not hear from the procurement department and that this already caused 2 days of delay for other subcontractors. The construction professional calls the procurement manager and learns that the department will approve the change requests immediately, but it took more time than anticipated because the formats of the change order and cost proposal did not comply with company procedures.
What should the construction professional have done to avoid the delay?