A construction company is executing a project for the restoration and expansion of electrical services for rural towns. The company is working with multiple several subcontractors on the project to reduce the risk of delays, compensate for lack of resources, and decrease completion time. Each subcontractor is responsible for managing their own interfaces; however, managing subcontractors’ relationships has become complicated due to constant incidents among subcontractors and delays occurring for some work packages. The interface monitoring process is not generating the expected result, resulting in many changes in the project.
What should the construction professional have done differently in this situation?