A construction professional’s project has multiple subcontractors, some of whom are interfacing among themselves during the construction life cycle. One of the construction professional’s team members explains that there was a variation claim submitted by one of the subcontractors. The team member received the substantiation from the subcontractor project manager who uses the contract drawing to prove that the scope is outside the contract. After reviewing this with the contract manager, the construction professional discovers that the subcontractor’s contract manager agreed to include this scope in the contract during the contract negotiation. but failed to communicate this to their project manager. What type of feedback loops should have been used to prevent this type of communication gap?