Question 50


An organization is starting a new project. The project is complex, and the client is using an architecture company for the initial phase. A construction professional has been selected as a general contractor for the execution phase and will need to engage subcontractors to deliver the project. What contract delivery method should the construction professional use to minimize the risk of claims?