PMI Construction Professional (PMI-CP) — Question 49
PMI CP Part 3 · question 49 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 49
During the final stage of the validate scope process of a construction project, a key stakeholder notices a defect in one of the HVAC systems that has been installed in one of the offices. The HVAC system was installed as designed. This was noted in a project completion report and sent to the construction professional. What should the construction professional do to resolve this issue?