PMI Construction Professional (PMI-CP) — Question 20
PMI CP Part 1 · question 20 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 20
A construction professional is considering contract structures for a small public facility. The program manager has advised that once the project budget has been determined there can be no cost increases or delivery delays. The scope is well-defined and the timeline is predictable. All prequalified contractors have completed many similar projects using the standard design.
Which contract structure should the construction professional use in this situation?