The construction of a multistory building has been completed. The contractor notified the owner that the facility’s construction, testing, and commissioning had been completed according to the contract documents. As-builts and warranties will be delivered to the owner’s office within 1 week after receiving the final payment. As an owner representative looking after the project, what should be the construction professional’s first step after receiving such a notice?