A construction professional is managing an 8-year-long, multibillion-dollar program. In the program’s third year, the construction professional starts noticing downward trends in the schedule and some milestones are being missed. The teams have started blaming one another for the delays, and the program is under varying degrees of oversight and public scrutiny.
What should the construction professional do to address this problem before it escalates further?