Question 119


During the implementation phase of a construction project, the access roads had to be closed temporarily to permit access for heavy machinery. The construction professional is aware that garbage disposal trucks will not enter the closed roads and will pick up the waste at a location outside the restricted area. Two weeks after handing over the first set of buildings to the end users, a few complaints were raised regarding the smell of garbage and delayed pickup.
What should the construction professional have done to prevent this from happening?