PMI Construction Professional (PMI-CP) — Question 119
PMI CP Part 6 · question 119 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 119
During the implementation phase of a construction project, the access roads had to be closed temporarily to permit access for heavy machinery. The construction professional is aware that garbage disposal trucks will not enter the closed roads and will pick up the waste at a location outside the restricted area. Two weeks after handing over the first set of buildings to the end users, a few complaints were raised regarding the smell of garbage and delayed pickup.
What should the construction professional have done to prevent this from happening?