QUESTION 41
What version number does the TOGAF ADM use to indicate that a high-level outline of the architecture is in place?
A. Version 0.9
B. Version 1.0
C. Version 0.1
D. Version 0.7
Correct Answer: C
QUESTION 42
Which of the following best describes the purpose of the TOGAF Library?
A. A portfolio of guidance material to support practical application of the TOGAF standard
B. A classification mechanism for artifacts and other outputs produced by execution of the TOGAF ADM
C. A series of documents that comprise the body of knowledge for TOGAF certification
D. A set of standard Reference Architectures that can be used within an enterprise architecture
Correct Answer: A
QUESTION 43
Complete the sentence. According to the TOGAF document, a(n)          is a representation of a system from the perspective of a related set of         .
A. architecture view, stakeholders
B. architecture viewpoint, architecture views
C. architecture viewpoint, stakeholders
D. architecture view, requirements
Correct Answer: A
QUESTION 44
What does the TOGAF standard classify as catalogs, matrices and diagrams?
A. Artifacts
B. Building Blocks
C. Deliverables
D. Models
Correct Answer: A
QUESTION 45
What technique used in Phase B provides a self-contained view of the business that is independent of the current organizational structure, business processes, information systems and applications?
A. Organization Map
B. Business Capability Map
C. Information Map
D. Value Stream Analysis
Correct Answer: B
QUESTION 46
Complete the sentence. The Enterprise Continuum provides methods for classifying architecture artifacts as they evolve from                 .
A. Foundation Architectures to re-usable architecture assets
B. generic solutions to Industry Models
C. generic architectures to reusable Solution Building Blocks
D. generic architectures to Organization-Specific Architectures
Correct Answer: D
QUESTION 47
Which one of the following best describes the purpose of a Change Request?
A. To request a dispensation or to kick-start a further cycle of architecture work
B. To review project progress and ensure the implementation is inline with the objectives
C. To ensure that information is communicated to the right stakeholders at the right time
D. To ensure that the results of a Compliance Assessment are distributed to the Architecture Board
Correct Answer: A
QUESTION 48
In which ADM phase does the value and change management process determine the circumstances under which the Architecture Development Cycle will be initiated to develop a new architecture?
A. Phase F
B. Phase G
C. Phase E
D. Phase H
Correct Answer: D
QUESTION 49
Complete the sentence. Actions arising from the Business Transformation Readiness Assessment technique should be incorporated in the          .
A. Architecture Roadmap
B. Communications Plan
C. Architecture Requirements Specification
D. Implementation and Migration Plan
Correct Answer: D
QUESTION 50
Which of the following best describes the TOGAF Architecture Governance Framework?
A. An example set of Architecture Principles
B. An approach to ensure the effectiveness of an organization’s architectures
C. An architecture of building blocks and corresponding standards, together with associated graphics
D. A reference model that includes information provider applications and brokering applications
Correct Answer: B
QUESTION 51
Which of the following describes a purpose of an Architecture Compliance review?
A. identifying the business transformation risks for an architecture project
B. identifying relationships between management frameworks
C. identifying stakeholders and their concerns
D. identifying where standards may require modification
Correct Answer: D
QUESTION 52
What ADM Phase generates the initial complete version of the Architecture Roadmap?
A. Phase F: Migration Planning
B. Phase B: Business Architecture
C. Phase E: Opportunities and Solutions
D. Phase D: Technology Architecture
Correct Answer: C
QUESTION 53
What is the purpose of the Standards Information Base within the Architecture Repository?
A. It lists the set of specifications to which architectures must conform
B. It describes the organization specific architecture framework and method
C. It provides standard templates and patterns that must be used to create new architectures
D. It provides a record of the governance activity across the enterprise
Correct Answer: A
QUESTION 54
In which phase of the ADM cycle do building blocks become implementation-specific?
A. Business Architecture
B. Technology Architecture
C. Opportunities and Solutions
D. Data Architecture
Correct Answer: C
QUESTION 55
Within the Architecture Repository, what does the class of information known as the Architecture Capability include?
A. Parameters, structures, and processes to support governance of the repository
B. The organization specific architecture framework, including a method for architecture development and a metamodel for architecture content
C. Specifications to which architectures must conform
D. Patterns, templates, and guidelines used to create new architectures
Correct Answer: A
QUESTION 56
What ADM phase includes establishing the Architecture Capability and definition of Architecture Principles?
A. Phase A: Architecture Vision
B. Phase B: Business Architecture
C. Preliminary Phase
D. Phase C: Data Architecture
Correct Answer: C
QUESTION 57
Complete the sentence. In ADM Phase H an architectural change known as a re-architecting change is driven by a requirement to                .
A. reduce investment
B. re-align with the business strategy
C. reduce costs
D. increase investment in order to create new value for exploitation
Correct Answer: D
QUESTION 58
Which of the following statements best describes the Requirements Management process?
A. The management of architecture requirements throughout the ADM cycle
B. The development of requirements for ADM Phase A
C. The prioritization and disposal of architecture requirements
D. The review of business requirements within the TOGAF ADM
Correct Answer: A
QUESTION 59
What is the first step in the architecture development Phases B, C, and D?
A. Conduct formal stakeholder review
B. Perform gap analysis
C. Develop Baseline Architecture Description
D. Select reference models, architecture viewpoints and tools
Correct Answer: D
QUESTION 60
What is an objective of the ADM Preliminary Phase?
A. To select and implement tools to support the Architecture Capability
B. To create the initial version of the Architecture Roadmap
C. To obtain approval for the Statement of Architecture Work
D. To develop a vision of the business value to be delivered by the proposed enterprise architecture
Correct Answer: A
We use cookies to improve your experience, including essential cookies required for the website to function. By continuing, you agree to our use of cookies. Learn more.
We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.
Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.
Advertisement cookies are used to provide visitors with customised advertisements based on the pages you visited previously and to analyse the effectiveness of the ad campaigns.
Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.