ITIL 4 Strategist Direct, Plan and Improve — Question 11
ITIL 4 Strategist Direct Plan And Improve Part 1 · question 11 of 39 in the ITIL 4 Strategist Direct, Plan and Improve question bank. Pick an answer to check it, or join the discussion below.
Question 11
A project team recently delivered a new service on time and to specification. However, the team encountered a number of issues during the project that resulted in an increase in the resources utilized. The project is about to close and the project team will immediately move on to the next project.
Which is the BEST way to avoid similar issues in the future?
Which is the BEST way to avoid similar issues in the future?