ITIL 4 Strategist Direct, Plan and Improve — Question 10
ITIL 4 Strategist Direct Plan And Improve Part 1 · question 10 of 39 in the ITIL 4 Strategist Direct, Plan and Improve question bank. Pick an answer to check it, or join the discussion below.
Question 10
Which concept or activity involves reviewing data to identify what is working well and what needs to be done differently?